Phase 5 — Supplier & Contracts#
Duration: ~4–6 weeks. Depends on: Inventory, MRP / PO partial.
Modules#
- Supplier Master
- Supplier Contacts
- Contracts
- Buyer Actions
- Purchase Orders
- PO Status / PO Upload / PO Recon
Tasks#
- Supplier API and PO API.
- Integrate with MRP and procurement planning from Phase 4.
Exit criteria#
- Supplier + PO APIs behind Phase 0 auth.
- End-to-end procurement flow from MRP suggestion → PO → receipt → invoice reconciles across both systems during dual-write.